A crane's proof load is a one time event and its inspection cycle is not

The load test proves the structure once. The inspection cycle is what keeps the proof true.

The load test proves the structure once. The inspection cycle is what keeps the pr
08 · Lifting · First Run Notes

Proof load, rated load and the gap between them

The rated load is what the crane may lift in service. The proof load is a larger load applied once, to demonstrate that the structure and the lifting gear have the margin the design assumed. The gap between them is deliberate and it is the reason a test is not a routine lift.

A proof load is typically a defined percentage above the rated capacity, applied to a new crane, to a crane after structural repair, and to a crane whose capacity has been reassessed. The percentage comes from the applicable standard, and the standard is the authority rather than the habit of the local inspector.

The distinction matters because a crane that has been overloaded in service has been proved by accident, at a load and in a direction nobody recorded. Such a crane needs an inspection rather than a certificate, and the inspection's scope is wider than a test's.

The proof load's result is not only a pass. It is a set of measurements taken before, during and after, and those measurements are what the future inspections will compare against.

What the test actually proves

A static proof test proves that the structure carries the load without permanent deformation. It does not prove that the crane will carry it repeatedly, and it does not prove that the brakes will stop it. Those are different claims and they need different tests.

The test's evidence is the absence of permanent set. A member that deflected under load and returned is carrying the load elastically. A member that deflected and stayed deflected has yielded, and the test has found the fault it was designed to find.

The measurement is therefore taken at two moments: loaded and after unloading. The difference between the pre-load and post-unload readings is the permanent set, and the tolerance for that difference is small and stated in the standard.

A test that reports only pass or fail has discarded its most useful output. A test that reports the deflection at load and the residual after unload has produced a baseline that later inspections can use, and later inspections always need one.

Static and dynamic tests and why both exist

The static test applies the proof load and holds it, to prove the structure. The dynamic test applies a smaller load and exercises the motions, to prove the machinery: hoist, trolley, travel, brakes and controls.

Holding a load is a structural event with almost no dynamic content. Moving a load is a machinery event with braking, acceleration and shock. A crane can pass a static test and fail a dynamic one in the brake, and the brake is the component most likely to injure somebody.

The dynamic test's load is usually lower than the proof load, because the purpose is to exercise the mechanisms rather than to stress the structure. The exact figure again belongs to the standard, and the figure matters less than performing the motions at the speeds the crane will use.

Both tests should be performed with the crane's actual operating configuration: the actual rope, the actual hook block, the actual reeving. A test performed with a lighter block has tested a different crane.

The measurement set: deflection, set, brake

Three measurements carry most of the value. Deflection at the load's position, which is the structural evidence. Residual deflection after unload, which is the yielding evidence. Brake stopping distance or time under the dynamic load, which is the machinery evidence.

Deflection is measured at a defined point, usually the bridge's centre or the girder's midpoint, with the trolley at a defined position. The position belongs in the record, because deflection depends on where the load hangs and a measurement without a position cannot be compared.

Brake performance is measured by stopping a moving load and observing the distance, or by a static brake test that applies the load and confirms it holds. A brake that holds a static load and slips on a moving one is a brake that will be found by the operator rather than by the inspector.

The record should also include the ambient temperature and the wind, where the crane is outdoors. Both change the readings and both are the first things questioned when a reading looks wrong.

Wire rope: the component with its own rules

Wire rope degrades by a set of mechanisms that are each visible: broken wires, wear on the outer wires, corrosion, and the loss of diameter that follows from both. It also degrades internally, where inspection cannot see, which is why the discard criteria are conservative.

The discard criteria are stated as counts and percentages: a number of broken wires in a length, a percentage loss of diameter, a degree of corrosion, a distortion of the lay. Each criterion is objective, and each is checkable with a gauge and a hand.

The inspection's coverage matters as much as its criteria. Rope that passes over a sheave has a wear pattern concentrated at the contact, and rope that is stationary at a termination has a corrosion pattern concentrated there. Both locations are where the criteria will be met first.

A rope replaced without a record of its condition at removal loses the chance to learn. The condition, the running hours and the duty are the three fields that make the next replacement predictable rather than reactive.

Limit switches, overload and the test that matters

A hoist limit switch is the component that prevents the hook block from reaching the drum. It is tested by running the hook up until the switch operates, and confirming that the motion stops with margin remaining. Testing it by pushing the lever with a hand tests the switch, not the system.

An overload limiter is tested by applying a known load and confirming the alarm and the cut-off at the stated points. The stated points are usually a warning at one percentage and a stop at a higher one, and both need to be demonstrated rather than assumed.

Both devices are frequently found to be present, functional, and set to a value that no longer matches the crane's capacity. A limiter set for a capacity the crane no longer has is a device that will either nuisance trip or fail to protect.

The test's record should state the load applied, the point at which the warning appeared, the point at which motion stopped, and the instrument used to weigh the load. A test with an unweighed load is a test of a device against an unknown.

The periodic inspection cycle and its intervals

Inspection intervals are set by regulation in most jurisdictions and by risk in all of them. The common structure is a frequent visual check by the operator, a periodic inspection by a competent person, and a thorough examination at a longer interval, with the intervals shortened for heavy duty.

Heavy duty is defined by duty class rather than by impression, and the duty class is a design input that should be on the crane's plate. A crane running at its rated load for most of its hours reaches its inspection criteria far sooner than one running at a fraction.

The interval is also shortened by events rather than by time: an overload, a shock load, a structural repair, a relocation, a change of duty. Each of those is a trigger for a thorough examination regardless of when the last one was performed.

The practical discipline is a register that holds both the calendar and the triggers, because a calendar alone will miss the crane that was overloaded in March and is due in November.

Records, tags and the audit trail

A crane's records should answer, for any date, three questions: what was inspected, by whom, and against what. The third question is the one that fails audits, because an inspection performed against a superseded standard is an inspection that cannot be defended.

The tag on the crane is the visible end of the record. A tag that states the next examination date is a tag that an operator can read, and an operator who can read it will report a crane whose tag has expired. A tag that states only a number is a decoration.

Photographs should accompany the written record at every thorough examination, particularly of the rope, the hook, the structure's joints and the brakes. Photographs date themselves, and a photograph from three years ago is the cheapest way to establish a trend.

The record's final value is in the comparison. A crane with five examinations on file is a crane whose degradation rate is known, and whose next repair can be scheduled rather than discovered.

What changes after a repair or a relocation

A structural repair resets the proof. The repaired member has a new stress history and a new set of welds, and the crane's capacity may be unchanged while its margin is not. A repair without a re-test is a repair without a proof.

A relocation resets almost everything. The runway changes, the foundations change, the alignment changes, and the inspection that was valid for the old installation describes a crane that no longer exists in that position.

A change of duty, from occasional to continuous, changes the inspection interval and the components' expected life. The change is usually commercial rather than technical, taken because a second shift was added, and the crane's register rarely follows it.

The discipline is a single rule: any event that changes the load path, the support or the duty triggers a re-test or a re-examination, and the trigger is recorded when the event is recorded rather than when the audit arrives.

The static and dynamic pair, and the triggers that shorten an interval, are set out in crane load testing and periodic inspection in the order an inspector will ask for them.

Checkpoints12
  • The proof load percentage is taken from the applicable standard, not from local habit.
  • Deflection is measured at a defined point with the trolley at a defined position.
  • Residual deflection is measured after unloading, as the permanent set evidence.
  • Brake performance is demonstrated with a moving load, not only a static hold.
  • Both static and dynamic tests are performed in the crane's real reeving and block.
  • Ambient temperature and wind are recorded with outdoor readings.
  • Wire rope is inspected at the sheave contact and at the termination, not only between.
  • Discard criteria are applied as counts and percentages, with a gauge.
  • Hoist limit is tested by running the hook up, confirming margin remains.
  • Overload limiter points are demonstrated with a weighed load and an identified instrument.
  • The inspection register holds both calendar intervals and event triggers.
  • Any structural repair, relocation or change of duty triggers a re-test or re-examination.