Commissioning runs in four stages and the last one is the one that hurts

Empty, single, interlocked, loaded. The order is not bureaucratic. It is the order in which faults become cheap to find.

Empty, single, interlocked, loaded. The order is not bureaucratic. It is the order
01 · Sequence · First Run Notes

Why the order is the method

Commissioning is usually described as the day the machine runs. It is better described as four gates, each of which releases one new variable and holds the others still. Nothing is under power that does not need to be, nothing carries material until the control logic has been proven.

The reason is not tidiness. A fault that appears with the machine empty, at low energy, is a fault you can locate with a meter and a drawing. The same fault, first seen with material flowing at rate, is a fault you locate by argument in a room with three companies in it.

Most projects invert the order for schedule reasons and run the whole line loaded on the first afternoon. The immediate result looks like progress and the cost arrives later, as a commissioning period that doubles and a warranty claim that nobody can trace to a stage.

Written into a purchase order, the four gates become payment milestones, and that single change does more for the quality of a handover than any amount of goodwill. Each gate has an exit condition, and the exit condition is a number, not a mood.

Stage one: the machine alone, with no material

The first stage runs each machine with its own controls and no material. Motors turn, axes stroke, cylinders extend, and nothing is asked to make a product. The purpose is to find the faults that belong to the machine rather than to the process.

The check list at this stage is short and unglamorous: rotation direction, end of travel, emergency stop, oil level, air pressure, abnormal noise, temperature rise over twenty minutes, and the position repeatability of every axis. Every item is cheap to fix now and expensive to fix later.

A stroke is not proof. Each axis should complete its full travel at least twenty times before the gate closes, because the failure modes that matter are not the ones that appear on the first move but the ones that appear after the hundredth, when a fixing has settled and a seal has taken its set.

Record the no-load current of every drive, the noise at each end of travel, and the repeatability figure measured with a dial indicator rather than read from the controller. The controller's own number tells you what the encoder believes, which is exactly what you will not be able to trust when the trouble starts.

Stage two: single units under their own control

Stage two energises one unit at a time. A conveyor section runs alone, one robot axis is jogged, one welding torch fires on a test coupon. Everything upstream is isolated, so any reaction belongs to that unit and to nothing else.

The value of isolation is diagnostic rather than operational. When a unit misbehaves with its neighbours dark, there are perhaps four candidate causes. When it misbehaves inside a live line there are forty, and half of them live in somebody else's cabinet.

The exit condition is a clean cycle count. Fifty consecutive cycles without an alarm, with the cycle time stable inside a band of a few percent, is a reasonable gate. Fewer cycles and you have not seen the intermittent fault; more and you are spending schedule on a unit that is already proven.

Two habits make this stage worth the time. First, write down the cycle count and the actual time, because the quote has a cycle time in it and the difference is the first honest number of the project. Second, run the unit at its slowest setting as well as its rated one, since some faults only appear when a motion is slow enough for a sensor to miss it.

Stage three: interlocked, with nothing moving that should not

Stage three puts every unit under one control with the material still out of the line. This is where handshakes, permissives, anti-collision zones and the safety circuit are proven. It is also the stage most often skipped, on the reasoning that nothing can be seen without product.

The reasoning is wrong. Interlocks are exactly the part of a system that can be tested with an empty line, and they are the part that is hardest to test once the line is full. A permissive that is wrongly wired will be masked by a full line and will surface as a crash, not as an alarm.

The core test at this stage is a deliberate upstream stop. Kill the supply, watch what the downstream units do, and check that each one stops where its logic says it should and resumes only when the permissive is genuinely restored. Do it at three different points in the cycle, because the state at the moment of the stop is what decides the recovery.

Then do it backwards. Fault injection at the sensor level, a disconnected photo-eye, a simulated safety door opening, a watchdog trip. A system that survives a clean stop and fails a dirty one has a recovery routine that has never been exercised, and the recovery routine is what the operator will meet at three in the morning.

Stage four: material, and only then rate

Stage four introduces product, and it introduces it slowly. Thirty percent of rated rate, then fifty, then seventy, then full. Each step is held until two things are true: the cycle time is stable and no new alarm class has appeared.

The faults that only appear with material are a distinct family: product that bridges, that sticks, that arrives rotated, that is lighter than the sample, that is heavier because it absorbed moisture overnight. None of them can be reproduced with an empty line, and all of them are cheaper to meet at thirty percent than at rated rate.

The staircase has a second purpose. The first rate at which something becomes unstable is a far more useful number than the rated rate, because it tells the owner where the margin is. A line that is stable to a hundred and ten percent has a different maintenance posture from one that starts shedding product at ninety.

Acceptance data should be taken at full rate, continuously, for at least two hours, and the two hours should include a shift change if the plant runs shifts. A four minute demonstration proves the machine can work. Two hours at rate proves it can work on a Tuesday afternoon when the compressed air is warm.

The instrument question

Commissioning arguments are usually about whether something is acceptable, and the argument is usually settled by whoever brought a measuring device. Bring the devices. A clamp meter, a pressure gauge with the right range, a vibration pen, a stopwatch, an infrared thermometer and a dial indicator cover most of what four stages need.

The instrument's paperwork belongs in the record alongside its reading. Model, range, calibration date and who took the measurement. A reading from an instrument with an expired calibration is not evidence, however plausible the number looks.

Range matters as much as accuracy. A gauge that reads to ten bar and is used on a line running at one bar has an error band wider than the tolerance being argued about. The same applies to a clamp meter on a drive whose no-load current is a tenth of its rating.

The cheapest recording method that survives is a fixed field table, one per stage, filled by hand and photographed at the end of each shift. Software is better when it exists, but a table with fixed fields beats a folder of screenshots every time, because a table can be compared and a screenshot can only be looked at.

What gets recorded, and by whom

Three classes of record carry almost all the value. State values, which are currents, pressures, temperatures and times. Action counts, which are cycles, strokes and starts. Exceptions, which are alarm codes with a one line description of what was happening when the code appeared.

The division of labour should be explicit. The operating company records state, because it will own the machine and will need the comparison later. The supplier records action counts, because it is proving its cycle time. Both sign the exceptions, because the exception is the only place where the two parties' interests genuinely differ.

The record's purpose is not archival. It is to answer one question three months later, when something fails: was it like this on the first day. Without a first day number, every failure is a debate. With one, the failure has a direction and often a rate.

This is also where the baseline for condition monitoring comes from, which is the subject of a later sheet. A vibration reading taken during stage four, at a known rate and a known load, is worth more than a hundred readings taken afterwards with no reference point.

Handover is a state, not a meeting

Handover is commonly treated as a signature, and a signature is a poor description of a state. The state is: four gates closed, records complete, spare parts list agreed with lead times, training done with named attendees, and the software and parameters handed over in a form the owner can restore.

Three gaps appear in almost every handover. The program backup is not supplied, or is supplied as a copy that cannot be restored without a licence the owner does not have. The parameter table is not supplied, so a drive replacement becomes a re-tuning project. The alarm code list is not supplied, so every fault starts with a call.

Each of these is cheap at handover and expensive afterwards, and each can be written as a condition: not provided, not complete. A handover checklist that says so is more useful than one that asks whether the machine is running, because the machine running is the thing everyone already agrees about.

The last item on a good handover list is the person. Who is called, at what number, for which class of fault, and what the response time is. A machine with a documented escalation path has a shorter average downtime than an identical machine without one, and the difference is not technical.

The gate that catches most faults

Across the projects that go badly, the pattern is consistent: two gates are merged into one, usually stages three and four, and the resulting fault is found under load. The cost of finding a fault under load is not twice the cost of finding it empty. It is the cost of the fault plus the cost of the material that was in the line.

The purchasing lever is simple and does not require technical knowledge. Four gates, four payment percentages, and the final percentage released only when the two hour run at rate has been signed. Suppliers who dislike the arrangement are usually the ones whose commissioning plan was going to be one afternoon.

For the owner, the arithmetic is worth stating plainly: a week spent on gates is a week off the front of the warranty period, and it is a week that removes most of the arguments that would otherwise occupy the first quarter of ownership.

None of this requires a large organisation. It requires a sheet of paper with four headings, a person who signs each heading, and the discipline to not move the paper forward until the heading is true.

A written sequence of this shape is what the commissioning checklist for industrial equipment sets out, and its stages map onto the four gates closely enough that one can be used as the other's check sheet.

Checkpoints12
  • Each gate has a written exit condition stated as a number, not as an impression.
  • Stage one completes with no material, no process fluids and no upstream power.
  • Every axis completes its full travel at least twenty times before the gate closes.
  • No-load current, end of travel noise and repeatability are recorded for every drive.
  • Stage two runs each unit isolated, with everything upstream de-energised.
  • Fifty consecutive clean cycles per unit, with cycle time stable inside a stated band.
  • Each unit is also run at its slowest setting, where sensor blindness hides.
  • Stage three includes a deliberate upstream stop at three different points in the cycle.
  • Fault injection is performed at sensor level, not only at the operator stop button.
  • Stage four steps rate in increments and holds each step until two conditions are met.
  • Acceptance data comes from a continuous run at rate of at least two hours.
  • Handover includes program backup, parameter table, alarm code list and named contacts.