Compressed air is the only utility nobody meters and everybody pays for

A leak audit at commissioning costs an afternoon and finds the joints that would otherwise leak for ten years.

A leak audit at commissioning costs an afternoon and finds the joints that would o
06 · Air · First Run Notes

Why air leaks survive every efficiency programme

Compressed air is generated centrally, distributed invisibly and paid for on a single invoice. No department owns the leaks, because no department sees them, and the cost is distributed across everything the plant makes.

The physics is unforgiving. Compressing air to seven bar takes roughly seven times the energy that the air delivers at the point of use, because most of the energy becomes heat that the compressor's cooling system then removes. A leak is therefore not a small loss of a cheap utility, it is a continuous payment on energy that has already been paid for once.

The scale is routinely underestimated. A single open three millimetre orifice at seven bar passes a volume that a small compressor produces, and a plant with fifty such joints is running a compressor for nothing. The joints are small enough to be ignored individually and large enough in aggregate to be a capital item.

The reason the problem persists is that fixing a leak has no visible benefit. The compressor's duty cycle changes slightly, the invoice changes slightly, and nobody connects the two. At commissioning, the connection is visible, because the baseline has just been measured.

The pressure drop chain from compressor to cylinder

Between the compressor's outlet and a cylinder's inlet there is a chain of pressure losses: aftercooler, dryer, filters, headers, tees, reducers, hoses, regulators and lubricators. Each has a small loss and the sum is what the cylinder actually receives.

The design mistake is to size the chain for the compressor's pressure and assume the point of use receives it. A system running at seven bar at the compressor and five and a half at the tool has lost a fifth of its stored energy in the chain, and the loss is paid for continuously.

Pressure drop also has a cost in hardware. A tool that needs six bar and receives five runs slower, wears faster and produces a worse result. The response is usually to raise the compressor's setpoint, which raises every leak's flow and every dryer's load.

The audit at commissioning is therefore a pressure survey: measure at the compressor, at each header, at each branch and at the point of use, under a representative load. The differences localise the problem, and the differences are usually larger than expected.

Where leaks concentrate in a new installation

Push to connect fittings are the largest single category in most audits, and they are also the easiest to fix. A tube that is not pushed fully home, a collet that has been disturbed, a tube cut with a dull blade and inserted anyway, all produce a leak that is silent and continuous.

Threaded joints come second, particularly where sealant was applied sparingly, or applied to the wrong part of the thread, or where a taper thread was tightened by feel. Threaded joints that are leak free at installation frequently leak after a season of thermal cycling.

Hoses and their couplings are third, and they are the category that degrades fastest, because a flexible hose is the only part of the system designed to move. A hose that is bent tighter than its specification will fail at the fitting rather than in the bore.

The fourth category is the deliberate opening: a blow off gun, a vacuum generator, an open ended line used for cleaning. These are not leaks in the technical sense and they are indistinguishable from leaks in the energy sense, and they are frequently the largest single item on the list.

An ultrasonic audit, hour by hour

An ultrasonic leak detector converts the turbulence at a leak into an audible signal in a frequency band where a workshop's ambient noise is low. The instrument is directional, so it localises, and it is sensitive enough to find a leak that a soap solution would miss.

The productive way to use it is to walk the system in a fixed order, at a fixed time, with the plant at a representative load. The order matters because the list is a checklist to be repeated next year, and a repeatable route produces comparable results.

Each finding is tagged physically with a number and recorded with the tag, the fitting type, the estimated flow and the action. The tag is what converts an audit into a work order, and the work order is what converts an audit into savings.

The time cost is real: a plant with a few hundred fittings takes most of a day for a first pass. The first pass finds the large leaks, which are a small proportion of the joints and a large proportion of the flow, so a first pass is disproportionately valuable.

Pressure drop is not a leak but it costs the same

A leak releases air to atmosphere. A pressure drop releases energy to friction inside the pipe. Both appear on the compressor's load and both are fixed by attention to the same components, and a leak audit that ignores restriction will miss half the opportunity.

Restriction is found by the same survey: a branch that shows a large drop between its header and its tools is a branch with an undersized line, a clogged filter or a partly closed valve. The fix is plumbing rather than maintenance, which is why it is often deferred.

Undersized lines are the common case in retrofitted plants, where a line was sized for four tools and now serves twelve. The line's velocity rises, the loss rises with the square of velocity, and the tools receive less pressure at exactly the time demand is highest.

A useful design target is a velocity in the distribution main that keeps the loss small relative to the compressor's pressure, and a velocity in the branch that keeps it small relative to the tool's requirement. Both are matters of diameter and both are decided at commissioning.

Sizing against real consumption, not installed capacity

Compressor capacity is usually selected from the sum of every tool's rated consumption, with a diversity factor applied by habit. The result is a machine that is oversized, running partly loaded, and therefore running at its least efficient point.

The measurement that matters is the actual flow at the actual duty. It can be taken with a flow meter, with a pump up test on the receiver, or by timing the compressor's loaded and unloaded periods against a known receiver volume. The last method needs no instrument beyond a stopwatch.

A pump up test at commissioning gives two numbers that stay useful for years: the total system volume and the leak rate when everything is closed. The leak rate is the number that a leak audit's savings are measured against.

The receiver's volume should also be checked against the demand profile rather than against a rule of thumb. A system with a large intermittent demand needs more storage than one with a steady demand of the same average, and the storage is what prevents the compressor from short cycling.

Dryers, drains and the water nobody plans for

Compressed air arrives at the dryer saturated, because compression concentrates the atmospheric water into a smaller volume. The dryer's job is to remove that water, and its performance is stated at a reference condition that the plant rarely matches.

A refrigerated dryer rated at a high inlet temperature and a high ambient delivers a different dew point in a cool plant, and a desiccant dryer rated at a low flow delivers a different dew point at its rated flow. The rating's condition belongs in the commissioning record.

Drains are the component that fails silently and expensively. A timer drain that is stuck open is a continuous leak. A trap that is stuck closed sends water downstream, where it corrodes tools and destroys instruments. Neither announces itself.

The commissioning check is simple: watch every drain through at least two cycles, and record whether it discharges water, air, or both. A drain that discharges air between water cycles is a drain that is wasting the compressor's output continuously.

The metering question and why it is political

Metering compressed air is the step that turns an efficiency programme from a proposal into a budget line. It is also the step that creates conflict, because a meter on a department's air line makes that department responsible for something it never paid for.

The compromise that works is a plant level meter plus a small number of sub meters on the largest consumers. The plant meter establishes the total and the trend; the sub meters establish who the largest consumers are and create the first basis for an internal charge.

The plant meter's most valuable output is not the daily total but the night time flow. A plant that is not producing and still drawing a substantial fraction of its daytime air has located its leaks without an audit, and the fraction is the leak rate.

At commissioning, the night time figure is the cleanest baseline available, because the plant is empty and every remaining flow is either a leak or a deliberate standing load. Recording it once, and again a month later, tells the whole story.

The arithmetic that justifies the audit

The saving from a leak programme is the reduced flow multiplied by the specific power of compression and by the hours the compressor runs. The specific power is a property of the compressor and is typically quoted in kilowatts per cubic metre per minute, and it rises sharply when the machine is lightly loaded.

The important subtlety is that savings do not accrue continuously. A compressor that runs loaded for fewer hours saves energy, and a compressor that is simply less loaded may save almost nothing if it is a fixed speed machine running unloaded half the time.

The correct framing is therefore in operating hours and in avoided capacity, and the avoided capacity is the number that justifies capital. A leak programme that removes enough load to defer the next compressor purchase is a programme with a very different return from one that merely trims a bill.

None of this requires the audit to be perfect. The first pass, done at commissioning with an afternoon and an ultrasonic detector, typically finds enough to pay for the detector and the time within a year, and it establishes the route and the record for every pass that follows.

The night time flow figure and the specific power arithmetic are the two numbers compressed air system efficiency uses to size a leak programme and to argue for it.

Checkpoints12
  • A pressure survey is taken at compressor, headers, branches and points of use.
  • The survey is taken at a representative load, not at a quiet moment.
  • A night time flow figure is recorded as the leak baseline.
  • A repeatable leak route is defined, with the system walked in a fixed order.
  • Every finding is tagged physically and recorded with fitting type and action.
  • Push to connect fittings are checked for full insertion and clean tube cuts.
  • Threaded joints are checked for sealant on the correct part of the thread.
  • Hoses are checked for bend radius against specification.
  • Deliberate open blowing is counted, since it costs the same as a leak.
  • Branch pressure drop is measured, not only leak flow.
  • Dryer rating conditions are recorded against the plant's actual inlet and ambient.
  • Every drain is watched through two cycles, for water, air, or both.