Acceptance is a set of numbers taken under stated conditions

A machine that holds its specification on a cold morning and misses it after four hours has not held its specification. The condition belongs in the sentence.

A machine that holds its specification on a cold morning and misses it after four
02 · Acceptance · First Run Notes

A number without a condition is an opinion

Every acceptance figure in a specification is shorthand for a longer sentence, and the shorthand drops the part that decides whether the number means anything. Cycle time, accuracy, repeatability, capacity and consumption are all conditional, and the condition is usually the ambient state of the plant.

A honest acceptance clause reads as: this value, measured by this method, at this location, with this instrument, under these conditions, over this duration. Four of those six clauses are normally missing, and the missing four are where the argument after handover lives.

The practical consequence is that acceptance should be written before the machine is ordered and re-read before it is measured. A specification that cannot be measured is not a specification, it is an aspiration, and an aspiration cannot be accepted or rejected.

The good news is that most conditions cost nothing to state. Ambient temperature, supply voltage, air pressure at the inlet, product variant and duration. Writing them down converts a debate into a table lookup.

Where the measurement is taken

The location of a measurement changes its value, and the change is often larger than the tolerance. Pressure taken at the compressor's outlet and pressure taken at the cylinder's inlet are two different pressures, separated by a filter, a regulator, forty metres of pipe and a leak.

Temperature is the clearest example. A spindle's temperature measured on the housing is not the bearing's temperature, and the difference widens as the machine warps. If the specification says the spindle holds its accuracy hot, the thermocouple belongs where the heat is generated, not where it is convenient.

For dimensional work, the location includes the fixture. A part measured on the machine's own fixture and the same part measured on a granite plate are not the same measurement, and both are legitimate, but only one of them answers the question the customer will ask.

The rule that survives contact with projects: state the location in the clause, draw it on a sketch, and attach the sketch to the acceptance record. A photograph of the probe in position is worth more than a paragraph describing where it was.

Accuracy against repeatability

These two words are used interchangeably in sales conversation and they should not be. Accuracy is how close the average lands to the commanded value. Repeatability is how tightly the outcomes cluster around their own average. A machine can be beautifully repeatable and consistently wrong.

The distinction changes what you do about a failure. Poor accuracy with good repeatability is a calibration or a compensation problem, and it is usually fixable in software. Good accuracy with poor repeatability is a mechanical problem, a thermal problem or a control loop problem, and software will not fix it.

Acceptance should therefore carry two numbers and not one, and the repeatability figure should be taken from a series rather than a pair. Twenty approaches to the same point, with the spread recorded, tells you what the machine will do tomorrow. Two approaches tells you what it did twice.

The third member of the family is resolution, which is what the scale can display and is almost always finer than either of the other two. A controller reading to a micron on a machine repeatable to twenty is not lying, it is simply reporting a smaller number than the one that matters.

Capacity at temperature, not at start

Rate and capacity are usually demonstrated on a machine that has been running for twenty minutes, in a bay that is cooler than the production hall, with the hydraulic oil at its nominal viscosity. All three of those conditions will be false in service.

The mechanism is straightforward. Oil thins as it warms, so a hydraulic system that holds pressure cold may lose speed hot. Air density falls with temperature, so a pneumatic system rated on a cool morning delivers less force by mid afternoon. Steel grows, so a fixture that holds a part at twenty degrees holds it differently at thirty five.

The acceptance answer is a soak. Run the machine until the temperatures stop climbing, then take the numbers. If the specification is meant to hold in production, the machine should be at production temperature when it is measured, and the record should show both the cold and the hot figures.

A machine that passes hot almost always passes cold, and the reverse is not true. So the hot test is the one to insist on, and the cold test is the one that is convenient to schedule.

The three documents that make a number usable

A number is usable when somebody else can reproduce it. That requires three documents, and projects that supply only the first one spend the next year re-litigating. The first is the acceptance record itself: value, unit, condition, instrument, time, signature.

The second is the method sheet: where the probe goes, how long it settles, how many samples are averaged, what is done about outliers. Without it, the same machine measured by two teams produces two numbers and a meeting.

The third is the configuration record: the parameters, the recipe, the tooling, the product variant that was running. A cycle time achieved on variant A says nothing about variant B, and the variant is the single most common missing field in a handover pack.

The three documents are cheap to produce during commissioning because the information is already in the room. They are expensive to reconstruct afterwards, because the people who knew are on another site.

Sampling: how many is enough

A sample of one is an anecdote. The question is how many samples make a claim, and the answer depends on what is being claimed. For a pass or fail against a limit, thirty samples gives a usable picture of the distribution's edge. For a demonstration that a defect rate is below a threshold, thirty is nowhere near enough.

A practical compromise used in machine acceptance is a short run of thirty for stability, plus a long run of two hours for rate. The short run answers whether the machine is behaving like itself. The long run answers whether it can keep behaving like itself.

Sampling also has to cover the cycle and not only the count. If the machine's cycle is forty seconds and the operator loads every twenty, the sample must include both loaded and unloaded conditions, or it will describe a machine that does not exist.

Attrition is the honest word for what happens to sample sizes in practice. The plan says thirty, the schedule allows eight, and the report says thirty. A report that states the actual number and the reason is more credible than one that states the plan.

The failure that passes acceptance

There is a class of fault that is present at acceptance and invisible to it, because it only shows under a condition the acceptance run never creates. The most common is a maintenance task that cannot be performed: a filter that cannot be reached, a grease point behind a guard, a sensor that needs a tool nobody stocks.

The second is a recovery path that has never been run. Acceptance tests the machine going forward. It rarely tests the machine after a mid-cycle stop with a part in transit, which is the state the operator meets most often.

The third is a consumable whose life is shorter than the service interval. A seal rated for two thousand hours on a machine serviced every four thousand is a planned failure that will be discovered as an unplanned one.

Each of these passes a numerical acceptance and fails ownership. The remedy is not more numbers, it is a walk-through with the person who will maintain the machine, before the scaffold comes down.

Custody of the instrument

When two parties measure the same thing and disagree, the disagreement is usually about the instrument rather than the machine. Different model, different range, different calibration date, or the same instrument used by two people with different hands.

The practical fix is custody: one instrument agreed in advance, one calibration certificate attached to the record, one person nominated to take the readings for both parties. This removes most disputes before they start, because a dispute needs two numbers.

Where the instrument is the owner's, it should be calibrated before the acceptance window and not after. A calibration performed after a failed test is indistinguishable from a calibration performed to explain the failure.

A cheap discipline helps: photograph the instrument's display at the moment of reading, along with the serial number. The photograph is not elegant and it has settled more arguments than any report.

Acceptance closes and warranty opens

The acceptance signature is also the moment the warranty clock starts, and the two events are usually treated as one, which is why they are usually both rushed. The signature should follow the record, and the record should be complete before the clock starts.

What the warranty will need is exactly the baseline: the numbers at handover, taken under stated conditions, with a method that can be repeated. A warranty claim that can compare a current reading with a handover reading is a different conversation from one that cannot.

The last clause worth writing is the remedy. If a figure drifts beyond a stated band, what happens. Adjustment, replacement, re-acceptance. Without that clause, drift becomes a negotiation, and negotiation is the most expensive form of maintenance.

Acceptance is therefore not the end of the project. It is the first data point of the machine's life, and it should be filed where the next data point can find it.

The discipline of condition, method and location described here is the discipline acceptance inspection practice for industrial equipment applies to a machine before anybody signs it off.

Checkpoints12
  • Every acceptance figure states value, method, location, instrument, condition and duration.
  • The measurement location is sketched and the sketch is attached to the record.
  • Accuracy and repeatability are recorded as two separate numbers.
  • Repeatability comes from a series of at least twenty approaches, not from two.
  • Rate figures are taken after a thermal soak, with the machine at production temperature.
  • Cold and hot figures are both recorded when the specification is meant to hold in service.
  • The method sheet states settling time, sample count and outlier handling.
  • The configuration record states the product variant and the parameters in use.
  • The actual sample size is reported, with the reason if it differs from the plan.
  • A maintainability walk-through happens before access equipment is removed.
  • One instrument is agreed in advance, with its calibration certificate in the record.
  • The record is complete before the warranty clock is started.